Trends in Transport Engineering and Applications
Cost Optimisation-A Case Study of Infrastructure Project
Abstract
The Double Deck component between Automotive Square and Gaddigodam comprised of main spine segment and two wing segments on either sides of spines. Both these spine and wing segment were pre-cast at casting yard and erected at site using double deck launching girder and wing erector system respectively. Further to integrate these components, stitch concrete is provided from bottom of wings using Manlift which required shuttering to be undertaken requiring a cycle time of 2 days. To overcome the time loss and also to enhance safety, a new concept was proposed which gave away the need of shuttering and heavy erection system. The proposed cost optimization solution also improvised the safety standards and provided an overall saving of 3 months and a cost saving of 94 lakhs. Keywords: Construction, Cost optimisation, Traditional construction, Double deck launchingReferences (7)
- Ali AS, Kamaruzzaman SN. Cost performance for building construction projects in Klang valley. J Build Perform. 2010;1.
- Parag Rajguru Anujaand Mahatme. Effective techniques in cost optimization of construction project. Int J Res Eng Technol. 2015;4:464-9.
- Georgekutty CK, Mathew George. Research methodology for material optimization in construction projects. Int J Eng Res Technol. August 2012;1:1.
- Akalya K. Rex. L. Kand Kamalnataraj. D. Minimizing the cost of construction materials through optimization techniques. IOSR J Eng. 2018:29-33.
- Bhushan Tatar, Rahul Patil. Time and cost optimization techniques in construction project management. Int J Latest Trends Eng Technol. 2021;7(3):230-7.
- Isidore LJ, Back WE. Multiple simulation analysis for probabilistic cost and schedule integration. J Constr Eng Manage. 2002;128(3):211-9. doi:10.1061/(ASCE)0733-9364(2002)128:3(211).
- Liu J, R ahbar F. Project time -cost tradeoff optimization by maximal flow theory. J Constr Eng Manage. 2004;130(4):607-9. doi:10.1061/(ASCE)0733-9364(2004)130:4(607).