Journal of Construction Engineering, Technology & Management Original Research

Integration of Revit to Microsoft Project for Construction Project Management: A Comparative Analysis of Scheduling and Resource Allocation

  1. Divyesh Solanki
  2. Chintan S. Raichura
  3. J. R. Pitroda
  4. Mukesh Macwan
  5. Yash Shah

Abstract

Building Information Modelling (BIM) has revolutionized the construction sector by having architectural, structural, and mechanical design on one 3D platform. Autodesk Revit application enables real-time updates and changes without increasing errors and omissions. Its parametric nature allows users to develop intelligent models, enhancing decision-making, resource allocation, and cost estimation. Revit's visual representation allows effective coordination and communication with stakeholders, promoting a higher degree of client satisfaction. The application and benefits of Revit and MSP in construction management and how it contributes to optimizing project efficiency, accuracy, and coordination are the focus of this article. The study Revit 3D planning, design and Microsoft Project (MSP) usage in construction project duration analysis. The methodology of research includes case studies qualitative data and quantitative data analysis, showing the interoperability of Revit and MSP in achieving project productivity maximization.

Keywords

References (27)

  1. K. Saeed and A. Sharma, “Visually Scheduling Construction Projects,” Constr. Reserch Congr., pp. 1–17, 2010.
  2. S. Karshenas and D. Haber, “Developing A Serious Game For Construction Planning and Scheduling Education,” Constr. Res. Congr., no. Mathiassen 1993, pp. 778–786, 2012.
  3. L. Hexu, L. Zhen, L. H. Xian, and M. Al-Hussein, “An Automatic Scheduling Approach: Building Information Modeling-Based On- site Scheduling for Panelized Construction,” Constr. Res. Congr. 2014, no. 2008, pp. 140–149, 2014.
  4. F. Rodrigues, A. D. Alves, and R. Matos, “Construction Management Supported by BIM and a Business Intelligence Tool,” energies, pp. 220–223, 2016.
  5. M. U. Deosarkar, D. R. Ballewar, R. R. Chitte, P. B. Swami, and N. S. Shirasath, “Analysis And Design of Multistoried Building by Using Revit BIM,” Int. J. Innov. Res. Technol., vol. 8, no. 1, pp. 1021–1026, 2021.
  6. Hadi AS, Abd AM, Mahmood M. Integrity of Revit with structural analysis softwares. IOP Conference Series: Materials Science and Engineering. 2021;1076(1):012119. doi:10.1088/1757-899x/1076/1/012119
  7. Habte B, Guyo E. Application of BIM for structural engineering: a case study using Revit and customary structural analysis and design software. Journal of Information Technology in Construction. 2021;26:1009-1022. doi:10.36680/j.itcon.2021.053
  8. Sampaio AZ, Gomes N, Gomes A. BIM design coordination: conflict analysis and construction simulation. Procedia Computer Science. 2024;239:49-57. doi:10.1016/j.procs.2024.06.145
  9. V. E. S. Mahendra Kumar, V. R. S. G, K. Keerthi, N. Sk, and P. Rakesh, “Residential Building Layout by using Rivet Software,” Int. J. Mod. Trends Sci. Technol., vol. 10, no. 03, pp. 40–45, 2024.
  10. P. M. Wale, N. D. Jain, N. R. Godhani, S. R. Beniwal, and A. A. Mir, “Planning and Scheduling of Project using Microsoft Project (Case Study of a building in India),” IOSR J. Mech. Civ. Eng. Ver. III, vol. 12, no. 3, pp. 2278–1684, 2015, doi:10.9790/1684-12335763.
  11. SHARMA A, PATHAK KK. MANPOWER PLANNING, SCHEDULING AND TRACKING OF A CONSTRUCTION PROJECT USING MICROSOFT PROJECT SOFTWARE. JOURNAL OF TODAY'S IDEAS - TOMORROW'S TECHNOLOGIES. 2015;3(2):161-169. doi:10.15415/jotitt.2015.32011
  12. R. J, A. A. Kelkar, and V. K. G, “Planning and scheduling of a multi- storeyed residential building with conventional execution approach as compared with application of project management techniques,” Int. Res. J. Eng. Technol., vol. 04, no. 07, pp. 2682–2685, 2017.
  13. P. Tripathi, V. K. Singh, P. S. Tomar, and J. P. Gupta, “Planning and Scheduling of Multistorey Rcc Building Using Microsoft Project,” Int. J. Eng. Sci. Invent. Res. Dev. Vol., vol. IV, no. Xi, pp. 356–364, 2018, [Online]. Available: www.ijesird.com
  14. P. P. Gauns and P. A. A. Kelkar, “IRJET- Application of Microso Project for Planning and Scheduling of a Residential Project,” Int. Res. J. Eng. Technol., vol. 06, no. 07, pp. 1191–1195, 2019.
  15. Tawale P. Planning and Scheduling of High-Rise Building using Primavera. International Journal for Research in Applied Science and Engineering Technology. 2020;8(5):1287-1290. doi:10.22214/ijraset.2020.5206
  16. Aldrin, “Planning and scheduling for multi-story building using M.S project,” Int. J. Adv. Res. Ideas Innov. Technol., vol. 7, no. 2, pp. 473–480, 2021, [Online]. Available: https://www.ijariit.com
  17. Shaikh A, Sankhe O, Ansari S, Sankhe C, Shelke M. Construction Management of a High Rise Structure Using MSP Software. International Journal of Innovations in Engineering and Science. 2021;6(5):01-04. doi:10.46335/ijies.2021.6.5.1
  18. M. K. Mahajan and P. M. Attarde, “Application of Microsoft Project Software in High-Rise Buildings .,” vol. 4, no. 5, pp. 1486–1488, 2022, doi:10.35629/5252-040514861488.
  19. V. S. Gohatre et al., “Planning Scheduling and Tracking of Residential Bungalo Using MSP,” Transportation (Amst)., vol. 3, no. 6, pp. 24–28, 2023.
  20. R. Bauchkar, S. Bele, P. Jadhav, R. Ambi, and M. Patilr, “A Review Paper on Building Planning and Scheduling Using Microsoft,” Int. J. Res. Publ. Rev., vol. 2, no. 12, pp. 1053–1064, 2021, [Online]. Available: www.ijrpr.com
  21. Taghaddos H, Hermann U, AbouRizk S, Mohamed Y. Simulation-Based Multiagent Approach for Scheduling Modular Construction. Journal of Computing in Civil Engineering. 2014;28(2):263-274. doi:10.1061/(asce)cp.1943-5487.0000262
  22. M. Korman, L. Simonian, and E. Speidel, “Using Building Information Modeling to Improve the Mechanical, Electrical, and Plumbing Coordination Process for Buildings,” AEI 2008 Build. Integr. Solut., 2008.
  23. Li Y, Li G, Wu S. Design and Practice of the Sand Table Simulation in Construction Project Management Teaching Based on BIM. ICCREM 2013. 2013:513-524. doi:10.1061/9780784413135.049
  24. K. Alomari, J. Gambatese, and M. J. Olsen, “Role of BIM and 3D Laser Scanning on Job Sites from the Perspective of Construction Project Management Personnel,” Constr. Res. Congr. 2016, no. Eastman 1999, pp. 2039–2049, 2016, doi:10.1061/9780784479827.203.
  25. Tayeh R, Issa RRA. Interactive Holograms for Construction Coordination and Quantification. Journal of Management in Engineering. 2020;36(6). doi:10.1061/(asce)me.1943-5479.0000847
  26. Y. H. Teo et al., “Enhancing the MEP Coordination Process with BIM Technology and Management Strategies,” Sensors, vol. 22, no. 13, 2022.
  27. Keshav, Singh EH. An Overview of Construction Management by Using Building Information Modelling Software with Integration of Augmented Reality. International Journal for Research in Applied Science and Engineering Technology. 2022;10(6):1112-1118. doi:10.22214/ijraset.2022.43973
Support