International Journal of Urban Design and Development Original Research

Identification and Assessment of the Factors causing Cost Overrun in Housing Projects

  1. A. Madhumitha School of Building and Environment, Sathyabama Institute of Science and Technology
  2. Priyadharshini . S Sathyabama Institute of Science and Technology,
  3. Surya Raj Kumar Sathyabama Institute of Science and Technology,

Abstract

Poor cost performance is a major problem in construction industry, especially in developing countries like India. Statistics reveal that majority of the projects faces the issue of cost overrun. The interrelationship between the causes of cost overrun and stakeholders has not been explored yet. The aim of the research is to minimize the effects of project cost overrun. The objective of the study is to categorize and rank the potential factors causing cost overrun. Further, it tries to provide suggestive framework to mitigate cost overrun which affects the project performance. Based on the expert interview and literature study, a questionnaire survey was framed and the results from the survey were validated through case studies. Nine factors were identified as critical factors causing cost overrun. From the findings, suggestive frameworks were proposed to overcome the issue of construction delay, poor communication and price escalation.

Keywords

References (17)

  1. Abdel-Monem M, El-Mohr AR, El-Dash K. Cost Overrun Gap Analysis In Construction Projects: State-Of-The-Art. Eng Res J-Fac Eng (Shoubra). 2022; 51(3): 76–97.
  2. Akhund MA, Khoso AR, Khan JS, Imad HU, Memon KM. Prompting cost overrun factors during PCP in construction projects. Indian J Sci Technol. 2019; 12(4): 1–7.
  3. Albtoush AF, Doh SI. A Review on causes of cost overrun in the construction projects. Int J New Innov Eng Technol. 2019; 12(3): 15–22.
  4. Annamalaisami CD, Kuppuswamy A. Reckoning construction cost overruns in building projects through methodological consequences. Int J Constr Manag. 2022; 22(6): 1079–1089.
  5. Deshmukh SS, Menkudle SD. Case study on “budget and schedule overrun during the construction phase of project. Int Res J Eng Technol (IRJET). 2019; 6(4): 353–356.
  6. El-Ahwal M, El-Attar SS, Abdel-Hafez WA. Factors leading to cost overrun occurrence in construction projects. Port-Said Eng Res J. 2016; 20(1): 71–77.
  7. Habibi M, Kermanshachi S, Safapour E. Engineering, procurement and construction cost and schedule performance leading indicators: state-of-the-art review. In Proceedings of Construction Research Congress. New Orleans, Louisiana: ASCE. 2018 Apr; 2–4.
  8. Ibrahim AH, Elshwadfy LM. Assessment of Construction Project Cost Estimating Accuracy in Egypt. Open Civ Eng J. 2021; 15(1): 290–298.
  9. Hwang BG, Shan M, Zhu L, Lim WC. Cost control in megaprojects: efficacy, tools and techniques, key knowledge areas and project comparisons. Int J Constr Manag. 2020; 20(5): 437– 449.
  10. Iyer KC, Jha KN. Factors affecting cost performance: evidence from Indian construction projects. Int J Proj Manag. 2005; 23(4): 283–295.
  11. Jayathilaka RDWW, Waidyasekara KGAS, Sirimewan DC. Impact of Material and Labour Cost Overruns on Contractors’ Budgeted Cost: The Case of Building Construction Projects in Sri Lanka. Proceedings of the International Conference on Industrial Engineering and Operations Management Monterrey, Mexico. 2021 Nov 3–5; 1089–1100.
  12. Karunakaran P, Abdullah AH, Nagapan S, Sohu S, Kasvar KK. Categorization of potential project cost overrun factors in construction industry. In IOP Conf Ser: Earth Environ Sci. 2018 Apr; 140(1): 012098. IOP Publishing.
  13. Keng TC, Mansor N, Ching YK. An Exploration of Cost Overrun in Building Construction Projects. Global Business & Management Research (GBMR). 2018; 10(3): 638–646.
  14. Perera BA, Perera CS, Jayalath C. Contractor’s perspective on key performance indicators of cost control in Asian, Middle Eastern, and European construction projects. International Journal of Construction Education and Research. 2022 Jul 3;18(3):217–33.
  15. Shaikh AN, Khatri AP, Dhavale TB. Application of Variance Analysis in Construction Cost Monitoring and Controlling. Int J Eng Res Technol. 2016 Jun; 6(5): 256–259.
  16. Shibani A, Arumugam K. Avoiding cost overruns in construction projects in India. Management Studies. 2015; 3(7–8): 192–202.
  17. Ullah K, Abdullah AH, Nagapan S, Suhoo S, Khan MS. Theoretical framework of the causes of construction time and cost overruns. In IOP Conf Ser: Mater Sci Eng. 2017 Nov; 271(1): 012032. IOP Publishing.