International Journal of Architectural Design and Planning Original Research

Study of Cost Overrun in Repair & Rehabilitation Projects in India

  1. Mohtashim Ahmad Siddiqui* Department of Building Engineering and Management, School of Planning and Architecture, New Delhi, India
  2. Luke Judson Department of Building Engineering and Management, School of Planning and Architecture, New Delhi, India.
  3. Sushil Kumar Solanki Department of Building Engineering and Management, School of Planning and Architecture

Abstract

In broad sense, the word "rehabilitation" suggested putting a building back to how it was before. The specialized area of repair and rehabilitation engineering necessitates knowledge and skills that go beyond those needed for design and construction engineering. Repair and rehabilitation projects are significantly more challenging and more complicated than new construction projects. It is vital to take a methodical approach to structural deterioration, and technology management and economics should coexist in harmony. Inadequate early planning and analysis before beginning a repair activity can harm the project's success in terms of time, cost, and quality. Critical factors of cost overrun in repair & rehabilitation can be categorized into different category on the basis of their severity & importance. So, it is necessary to understand the cost impact of those cost overrun factors. Cost overruns leading to the financial crisis and hence these costs overrun factors must be identified and ranked so that they can be mitigated at very early stage. The goals of this study are to identify the critical factors that cause cost overrun in repair & rehabilitation projects through field study & expert interviews and analyze them through statistical tool (Cronbach’s alpha & Friedman test) to check reliability and significance as well as solutions to mitigate the cost overrun in Repair & Rehabilitation projects. As repair and rehabilitation projects are more complex and complicated than standard construction projects, poor estimates, a lack of condition assessment or visual inspection, and contractor incompetence by providing a lower quote than the projected cost may result in cost overruns. Analyzing the productivity, schedule, and cost for certain tasks may be effectively

Keywords

References (12)

  1. Abdussalam Shibani, K. A. (2015). Avoiding Cost Overruns in Construction Projects in India. Management Studies, August 2015, Vol. 3, No. 7-8, 192-202, pp. 192-202.
  2. Bhattacharjee, J. (2016). Repair, rehabilitation & retrofitting of RCC for sustainable development. Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2.
  3. Chajlani Jeetendra, K. S. (2015). Analysis of repairs and rehabilitation of R.C.C Structures. International Journal of Engineering Associates,Volume 4, Issue 8
  4. Chander, S. (2014). Rehabilitation of Buildings. International Journal of Civil Engineering Research, Volume 5, pp. 333-338.
  5. CPWD. (2011). Handbook on Repair & Rehabilitation of RCC Buildings. New Delhi: CPWD.
  6. Pankaj Lipte, A. G. (2020). Structural Audit, Repair and Rehabilitation Techniques. International Research Journal of Engineering and Technology (IRJET), Volume 7. Issue 9, pp. 2809-2814.
  7. Shweta M. Kadam, S. C. (2016). SOME STUDIES ON COST OVERRUN FACTORS AFFECTING REPAIRS AND REHABILITATION OF BUILDINGS. International Journal of Civil Engineering (IJCE), Volume 5, Issue 6, pp. 51-56.
  8. Singh, P. (2021). Techno Managerial Challenges in Repair & Rehabilitation of Tall RCC Building Structure. New Delhi.
  9. Sreekumar, A., Paul, D. V., Solanki, S. K., & Dua, S. (April 2022). Sustainable Retrofit for Adaptive Building Reuse–A Facility Management Approach for Highlighting and Cataloguing Deficiencies for Retrofit Decision Making. International Journal of Multidisciplinary Innovative Research, ISSN: 2583-0228 Volume 2, Number 2, pp-21-37.
  10. Suresh Kumar S, M. M. (2019). AN EXPERIMENTAL STUDY OF REPAIR AND REHABILITATION OF STRUCTURE. International Journal of Scientific & Engineering Research Volume 10, Issue 3.
  11. Sushil Kumar Solanki, V. P. (May 2022). Comparison between service life prediction methods for building rehabilitation: application on a case study. Journal of Building Pathology and Rehabilitation (2022) 7:51.
  12. Varinder K Singh. (2013). Structural Repair and Rehabilitation of 3 no. (G+8) multi-Story residential building. Procedia Engineering (pp. 55-64).
Support