International Journal of Architectural Design and Planning Review Article

Impact of Project Complexities on Cost Overruns

  1. Gopika Nair* Department of Building Engineering and Management, School of Planning and Architecture
  2. Sushil Kumar Solanki Department of Building Engineering and Management, School of Planning and Architecture

Abstract

As decision-making and goal setting become more challenging due to complexity, there is growing consensus that comprehending complexity is essential for project management. However, there have been concerns expressed regarding how complexity can be quantified in a reliable way that takes into account structural, dynamic, and interaction factors. Current operational definitions of complex projects based on size and budget, have been called into doubt. What can be done is to rank complexities based on their impact and focus on the most impactful complexity dimensions to keep a check on cost overruns leading from them. This study addresses the challenging issues of defining complexity and a complex construction project from the literature and the field. To continue the analysis of the phenomena mentioned in this initial study, a research agenda is suggested. The project complexity uncertainties that could have positive or negative effects on the project's cost and timeline performance can be reduced as a consequence of this investigation. The comprehensive checklist developed for complexity dimensions will serve as a checklist for project managers for identifying which of these dimensions and how many of them are present at each stage of a construction project; and the mitigation strategies that can be adopted at each stage to have a tight grip on project cost.

Keywords

References (47)

  1. Trice, J. B. (1971). A re-examination of the relations between size and various components of organisational complexity. Administrative Science Quarterly.
  2. Maximiano, A. C. A. (1997). Administração de projetos: como transformar idéias em resultados. In Administração de Projetos: como transformar idéias em resultados (pp. 196-196).
  3. A.D., B. D. (2003). Modelling global risk factors affecting construction cost performance. International Journal of Project Management.
  4. Sahu, P. K. (2022). Defects in Concrete in Building Construction. Journal of Advances in Geotechnical Engineering, 5(2).
  5. Avotos, I. (1983). Cost-relevance analysis for overrun control. International Journal for Project Management, 142-148.
  6. Baccarini, D. (1996). The concept of project complexity, a review. International Journal of Project Management, Vol.14, Issue 4.
  7. Biggiero, L. (2001). Sources of Complexity in Human Systems. Nonlinear Dynamics Psycology and Life Sciences.
  8. Bosch-Rekveldt, M. J. (2011). Grasping project complexity in large engineering projects: The TOE (Technical, Organizational and Environmental) framework. International Journal of Project Management-Volume 29, Issue 6, 728-739.
  9. Cilliers, P. (2005). Complexity, deconstruction and relativism. Theory, culture & society, 22(5), 255-267.
  10. Dizikes, P. (2010, June 2nd). Explained: Knightian uncertainty. Récupéré sur MIT News: https://news.mit.edu/2010/explained-knightian-0602
  11. Dziadosz, A., & Rejment, M. (2015). Risk analysis in construction project - chosen methods. Procedia Engineering Volume 122.
  12. Edmonds, B. (1999). Syntactic Measures of Complexity. Manchester: University of Manchester.
  13. Fitsilili, P. (2009). Measuring the complexity of software projects. WRI World Congress on Computer Science and Information Engineering, Computer Science and Information Engineering, (pp. 644–648). Washington D.C.
  14. Genelot, D. (2001). Manager Dans La Complexité- Réflexions À L'usage Des Dirigeants. Insep Consulting.
  15. Geraldi, J. (2008). Patterns of complexity: The thermometer of complexity. Project Perspectives, 24, 4-9.
  16. Gidado, K. (1996). Project complexity: the focal point of construction production planning. Construction Management and Economics.
  17. Girmscheid, G., & Brockmann, C. (2008). The Inherent Complexity of Large Scale Engineering Projects. Project Perspectives 29.
  18. Hage, R. D. (1978). Size, Technology, Complexity, and Structural Differentiation: Toward a Theoretical Synthesis. Sage Publications Inc., 26.
  19. Harty, C. G. (2007). The futures of construction: A critical review of construction future studies. Construction Management and Economics, 477-493.
  20. He, Q. L. (2015). Measuring the complexity of mega construction projects in China—A fuzzy analytic network process analysis. International Journal of Project Management-Volume 33, Issue 3,, 549-563.
  21. Hossny, H. E., Ibrahim, A. H., & Elnady, A. (2021). Assessment of Construction Project Complexity. The Open Civil Engineering Journal, 10.
  22. Hughes, A. D. (2000). The influence of project complexity on estimating accuracy. 16th Annual ARCOM Conference. Glasgow: Reading, Association of Researchers in Construction Management
  23. J. G. Geraldi, &. G. (2007). On faith, fact, and interaction in project. Project Management Journal, 32–43.
  24. J. R. Turner, &. R. (1993). Goals and methods matrix: Coping with projects with ill defined goals and/or methods of achieving them. International Journal of Project Management, 93–102.
  25. Jeff C. Clements, J. S. (2022). Meta-Analysis Reveals an Extreme "Decline Effect" in the Impacts of Acidification on Fish Behaviour. PLoS Biology.
  26. M. V. Tatikonda, S. R. (2000). Technology novelty, project complexity, and product development project execution success: A deeper look at task uncertainty in product innovation. IEEE Transactions on Engineering Management, 74–87.
  27. Mansfield, J. C. (1972). Technology, Size and Organisation Structure. Sage Journal.
  28. Memon A.H., R. I. (2011). Identifying construction resource factors affecting construction cost: Case of Johor. Malaysian Technical Universities International Conference on Engineering & Technology. Johor.
  29. Mohr, L. (1971). Organisational Technology and Organisational Structure. Administrative Science Quarterly.
  30. Morel, B. &. (1999). Through the looking glass of complexity : the dynamics of organizations as adaptive and evolving systems. Organization Science Vol.10, No.3,.
  31. P. A. Koushki, K. A.-R. (2005). Delays and cost increases in the construction of private residential projects in Kuwait. Construction Management and Economics, 285-294.
  32. Perrow, C. (1961). Analysis of Goals in Complex Organisations. American Sociological Review, 26.
  33. Pollak, J. (2007). The changing paradigms of project management. International Journal of Project Management, 266–274.
  34. Pugh, D. (1968). Dimensions of Organisational Structure. Administrative Science Quarterly.
  35. Safapour E, Kermanshachi S, Habibi M, Shane J. Resource-Based Exploratory Analysis of Project Complexity Impact on Phase-Based Cost Performance Behavior. Construction Research Congress 2018. 2018:439-448. doi:10.1061/9780784481271.043
  36. Schlindwein, S. L., & Ison, R. (2004). Human knowing and perceived complexity: implications for systems practice. Emergence: Complexity and Organization, 6(3), 27-32.
  37. Sinha, S. T. (2001). A complexity index for the design process. International Conference on Engineering Design, ICED’01, Vol.1,. Glasgow: Professional Engineering Publishing.
  38. Vidal, L. M. (2007). Modelling Project Complexity. International Conference on Engineering Design, ICED'07. Paris.
  39. Williams, T. M. (1999). The need for new paradigms for complex projects. International Journal of Project Management, 269–273.
  40. Paul, V. K., Solanki, S., & Dasgupta, R. (2021). Post Pandemic Impact on Planning Of District Hospitals in India. International Journal of the Built Environment and Asset Management, 2(1), 1. https://doi.org/10.1504/IJBEAM.2021.10043515
  41. Kapoor E, Solanki SK, Paul VK. Cost benefit analysis for rehabilitation of buildings: case of Indian Medical Association, New Delhi. International Journal of Structural Engineering. 2021;1(1):1. doi:10.1504/ijstructe.2021.10043508
  42. Moza, Amit., Paul, V. K., & Solanki, S., (2022). Methodology for Establishing a Model for Assessing Performance of Public Projects in India. International Journal of the Built Environment and Asset Management, Inderscience publisher.
  43. Rastogi R, Solanki SK, Paul VK. Analyzing the Impact of Challenges in Prefabricated Building Construction Supply Chains. Journal of Engineering Research and Sciences. 2022;1(5):71-82. doi:10.55708/js0105008
  44. International Journal of Architecture and Infrastructure Planning. doi:10.37628/ijaip
  45. SK Solanki, R Rastogi, VK Paul; Cost Analysis of Functional Retrofitting Measures in Buildings Journal of The Institution of Engineers (India): Series A (2022, 103 (3), 725-732
  46. Singh, V., Paul, V. K., & Solanki, S. K. (2022). Feasibility Study of Adaptive Reuse of Old Buildings. International Journal of Housing and Human Settlement Planning, 8(1), 10-31p.
  47. Kumari, N., Taran Sidana, V. K., & Paul, S. K. S. (2022). Analysis of Smoke Production and Movement in shopping malls/Centers. International Journal of Town Planning and Management, 8(1), 1-23p.
Support