Journal of Construction Engineering, Technology & Management
Comparative Study of Schedule Analysis Using Earned Value and Earned Schedule Methods on Two Distinct Construction Projects
Abstract
This paper focuses on how Earned Value (EV) and Earned Schedule (ES) is used for schedule analysis to monitor the progress and forecast important information in schedule; well before it is too late to make any corrective changes. Two case studies are adopted here. Using Earned Value, its monthly performance is computed along with project completion date is forecasted. The reliability of the two methods is compared using correlation analysis between the two case studies and it is seen that the dependency between the earned schedule variables between the two case studies are higher than that of the earned value ones.Keywords: Earned value, Earned Schedule, Schedule analysis, reliability, correlationReferences (9)
- Fleming, Quentin W, Joel M Koppelman. Earned Value Project Management . Newtown Square, Pa.: Project Management Institute, 2010. Print.
- Fleming Q, Koppelman J. What’s Your Project’s Real Price Tag ?, Harvard Bus Rev. 2003; 81(9): 20–21p.
- Abba Wayne, How Earned Value Got to Prime Time: A Short Look Back and Glance Ahead, The Measurable News , Spring, 2001.
- Presutti, Anthony H. Jr. Cost/Schedule Control Systems Criteria: A Government Process That May Work, The Gov Accountants J. 1993; 42(1): 47p.
- Mukho S, Lisanti J. Application of Earned Value for Small Project Control: Panacea or Bane, AACE Transactions , 1982; A.1.1.–A.1.5.
- Adamczyk WF. EV - Not Only for Large Projects, AACE Transactions, 1989; J.2.1– J.2.5.
- Walt Lipke, Kym Henderson, Earned Schedule …an emerging enhancement to EVM, Projects & Profits , February 2007, Reprint of November 2006 CrossTalk article.
- Walt Lipke, Kym Henderson, Earned Schedule – A Quantum Advance , APM Yearbook, UK J. 2006.
- Kym Henderson, Earned Schedule: A Breakthrough Extension to Earned Value Management, Proceedings of PMI Global Congress Asia Pacific 2007, January 2007. % delay using EACt of both case studies % delay using IEAC of both case studies Series1 -0.69 0.84 -1.00 -0.50 0.00 0.50 1.00 EVM % DELAY vs ES % DELAY Cite this Article Prakash Rao B, Jacob Cherian, Leon Jeremiah, Comparative Study of Schedule Analysis Using Earned Value and Earned Schedule Methods on Two Distinct Construction Projects , Journal of Construction Engineering, Technology and Management. 2015; 5(3): 1–5p.