Improved Software Cost Estimation using General Search based Analogous Project Feature Weight Assignment
Abstract
Software cost estimation is the estimation of development effort and time required to develop any software project. Analogy based estimation is considered as one of the most popular techniques used in software cost estimation. Analogy based estimation is mostly appraised for its expensive computation cost , low prediction accuracy and large memory requirements despite many research works focusing on optimizing the weights of the project features being carried out in past for the overall purpose of improvement in performance of analogy based software cost estimation. In this paper, a general search based feature weight assignment has been proposed for improving the analogous based software cost estimation. Here in this proposed work, separate weights to each project feature and to find the optimal weights by general search is done. The proposed approach has been exercised on several real-world data sets like Albrecht and Desharnais and evaluated using commonly used quality metrics like Mean of Magnitude of Relative Error (MMRE). The promising results achieved from the study were found to increase estimation accuracy and reliability which likely increases the models chance of acceptance too.Keywords: Analogous Based Estimation, Feature Weight Assignment, General Search, Software Cost EstimationCite this ArticleZahid Hussain Wani Improved Software Cost Estimation using General Searchbased Analogous Project Feature Weight Assignment Journal of Advances in Shell Programming . 2019; 6(1) : 20 26p.References (34)
- Pendharkar PC, Subramanian GH, Rodger JA. A probabilistic model for predicting software development effort.IEEE T Softw Eng. 2005;31(7): 615–624p.
- Auer M, Trendowicz A, Graser B, Haunschmid E, Biffl S. Optimal project Improved Software Cost Estimation Zahid Hussain Wani JoASP (2019) 20-26 © STM Journals 2019. All Rights Reserved Page 25 feature weights in analogy -based cost estimation: Improvement a nd limitations.IEEE T Softw Eng.2006; 32(2): 83–92p.
- Jorgensen M, Shepperd M. A systematic review of software development cost estimation studies. IEEE T softw Eng. 2007;33(1): 33–53p.
- Boehm B, Abts C, Chulani S. Software development cost estimation approaches— A survey. Ann Softw Eng . 2000; 10(1–4): 177–205p.
- Boehm BW. Software engineering economics.IEEE T Softw Eng . 1984; (1): 4–21p.
- Huang X, Ho D, Ren J, Capretz LF. Improving the COCOMO model using a neuro-fuzzy approach. Appl Soft Comput . 2007;7(1): 29–40p.
- Jensen R. An improved macrolevel software development resource estimation model. In 5th ISPA Conference . 1983, April; 88–92p.
- Putnam L. Measures for Excellence , Putnam, L. and Myers, W., 1992.
- Helmer O, Brown B, Gordon TJ. Social Technology.[By] Olaf Helmer.[With] Contributions by Bernice Brown, Theodore Gordon. Basic Books, 1966.
- Heiat A. Comparison of artificial neural network and regression models for estimating software development effort.Info Softw Technol. 2002; 44(15): 911–922p.
- Shin M, Goel AL. Empirical data modeling in software engineering using radial basis functions. IEEE T Softw Eng . 2000;26(6): 567–576p.
- Oliveira AL. Estimation of software project effort with support vector regression.Neurocomputing.2006; 69(13– 15): 1749–1753p.
- Tausworthe RC. The work breakdown structure in software project management.J Syst Softw . 1979; 1: 181– 186p.
- Jørgensen M. Top -down a nd bottom -up expert estimation of software development effort.Info Softw Technol . 2004; 46(1): 3– 16p.
- Mendes E, Mosley N, Counsell S. Investigating Web size metrics for early Web cost estimation. J Syst Softw . 2005;77(2): 157–172p.
- Costagliola G, Ferrucci F, Tortora G, Vitiello G. Class point: an approach for the size estimation of object -oriented systems.IEEE T Softw Eng . 2005; 31(1): 52–74p.
- Miyazaki Y, Terakado M, Ozaki K, Nozaki H. Robust regression for developing software estimation models. J Syst Softw. 1994;27(1): 3–16p.
- Madachy RJ, Khoshnevis B. A software project dynamics model for process cost, schedule and risk assessment [Doctoral dissertation], University of Southern California, 1994.
- Chulani S, Boehm B, Steece B. Bayesian analysis of empirical software engineering cost models. IEEE T Softw Eng . 1999;25(4): 573–583p.
- MacDonell SG, Shepperd MJ. Combining techniques to optimize effort predictions in software project management. J Syst Soft.2003; 66(2): 91–98p.
- Shepperd M, Schofield C. Estimating software project effort using analogies.IEEE T Softw Eng .1997;23(11): 736–743p.
- Sternberg RJ. Component processes in analogical reasoning. Psychol Rev. 1977;84(4): 353p.
- Huang SJ, Chiu NH. Optimization of analogy weights by genetic algorithm for software effort estimation. Info Softw Technol. 2006;48(11): 1034–1045p.
- Chiu NH, Huang SJ. The adjusted analogy-based software effort estimation based on similarity distances. J Syst Softw . 2007;80(4): 628–640p.
- Wieczorek I. Improved software cost estimation–a robust and interpretable modelling method and a comprehensive empirical investigation. Empir Softw Eng. 2002;7(2): 177–180p.
- Myrtveit I, Stensrud E. A controlled experiment to assess the benefits of estimating with analogy and regression models.IEEE T Softw Eng . 1999); 25(4): 510–525p.
- Finnie GR, Wittig GE, Desharnais JM. A comparison of software effort estimation techniques: using function points with Journal of Advances in Shell Programming Volume 6, Issue 1 ISSN: 2395-6690 (Online) JoASP (2019) 20-26 © STM Journals 2019. All Rights Reserved Page 26 neural networks, case-based reasoning and regression models. J Syst Softw. 1997;39(3): 281–289p.
- Auer M, Graser B, Biffl S. An approach to visualizing empirical software project portfolio data using multidimensional scaling. In Proceedings Fifth IEEE Workshop on Mobile Computing Systems and Applications . IEEE, 2003, October 504–512p.
- Walkerden F, Jeffery R. An empirical study of analogy -based software effort estimation.Empir Softw Eng . 1999; 4(2): 135–158p.
- Mendes E, Watson I, Triggs C, Mosley N, Counsell S. A comparative study of cost estimation models for web hypermedia applications.Empir Softw Eng . 2003; 8(2): 163–196p.
- Shepperd M, Schofield C, Kitchenham B. Effort estimation using analogy. InProceedings of the 18th International Conference on Software Engineering, IEEE Computer Society,1996, May 170–178p.
- Albrecht AJ, Gaffney JE. Software function, source lines of code, and development effort prediction: a software science validation. IEEE T Softw Eng . 1983; (6): 639–648p.
- Desharnais JM. Analyse statistique de la productivitie des projects informatique a partie de la technique des point des function, [ Master’s Thesis], University of Montreal, 1989.
- Kemerer CF. An empirical validation of software cost estimation models. Commun ACM. 1987;30(5): 416–429p. Cite this Article Zahid Hussain Wani . Improved Software Cost Estimation using General Search based Analogous Project Feature Weight Assignment. Journal of Advances in Shell Programming. 2019; 6(1): 20–26p.